Maintenance strategy and budget

Status
In effect

Each year Aurizon Network engages with stakeholders through the Rail Industry Group to develop its maintenance and renewals strategies and budgets for the following year.

If a special majority of end users in a system vote not to approve Aurizon Network’s final draft maintenance strategy and budget, then Aurizon Network must seek approval from the QCA.

Newlands system, 2021–22

On 3 March 2021, Aurizon Network sought our approval for its FY22 maintenance strategy and budget for the Newlands system.

We are satisfied that the activities and costs specified in the maintenance strategy and budget are prudent and efficient. Therefore, we have approved the Newlands FY22 maintenance strategy and budget as submitted by Aurizon Network.

Title Document
26 May 2021 Final report QCA – Newlands FY22 maintenance strategy and budget – letter and decision notice pdf, 391.23 Kb
Title Document
03 March 2021 Submission Aurizon Network – Maintenance Strategy and Budget 2021-22 letter and submission pdf, 213.30 Kb
03 March 2021 Submission Aurizon Network – Maintenance Strategy and Budget 2021-22 Appendix E Newlands Redacted pdf, 5.49 Mb
Title Document
23 April 2021 Submission Aurizon Network – response to stakeholder submissions pdf, 4.23 Mb
20 April 2024 , NaN b
Title Document
26 March 2021 Submission Glencore – Newlands FY22 MSB – submission pdf, 233.82 Kb
26 March 2021 Submission RIG – Newlands FY22 MSB – submission pdf, 827.36 Kb