Queensland Rail's DAAU to change the reference train service

Status
In progress

Queensland Rail submitted a draft amending access undertaking (DAAU) to amend the characteristics of its reference train service in schedule D of its 2016 access undertaking.

We invited stakeholders to comment and received submissions from Yancoal, New Hope and Aurizon Coal.

Queensland Rail’s Reference Train Service DAAU, stakeholder submissions and our stakeholder notice are available for download below.

We are also considering a reference tariff variation that will reflect, among other things, the proposed amended reference train characteristics

Date Action
30 September 2019 We published Queensland Rail’s reference train service DAAU and invited stakeholder submissions
22 October 2019 Stakeholder submissions period closed—three submissions received