We reviewed the DAAU and accepted the inclusion of the outstanding 7x expansion costs into the regulated asset base as reasonable.

No stakeholders made any submissions, and on 15 December 2011, the QCA made a final decision to approve DBCT Management’s DAAU.

Show more

On 7 November 2011, the QCA received from DBCT Management an application to approve a
draft amending access undertaking (DAAU) for the coal handling services at the Dalrymple Bay Coal
Terminal.

The DAAU requested approval to amend the regulated asset base, revenue and tariff based on
$8.7 million in outstanding expenditures related to the 7x expansion of the terminal.

Show more
  • 5 December 2011
Project Timeline

Submissions on DAAU

This project is complete

No submissions were received